PE Pipe Butt Fusion Welding Procedure


Butt Fusion Welding

1. Preparation: Place the pipe or pipe fitting in a flat position on the butt fusion machine with a cutting allowance of 10-20mm.

2. Clamp: According to the welded pipe, pipe fitting selection to verify the slip fixture, clamping pipe, ready for cutting.

3. Cutting: Cutting the welded pipe section, the impurities and oxide layer on the end face of the pipe fittings ensure that the two butt ends are smooth and free of impurities.

4. Defouling: Dip cotton yarn into alcohol, clean and wipe the pipe head, remove dust and dirt.

5. Alignment: The end faces of the two welded pipe sections should be completely in alignment, and the wrong side should be as small as possible. The wrong side should not exceed 10% of the wall thickness. Otherwise, the welding quality will be affected.

6. Heating: The butt temperature is generally between 210-230℃. The heating time of the heating plate is different in winter and summer, and the melting length of the two ends is 1-2mm.

7. Switch: Remove the heating plate, quickly let the two hot melt end face phase bonding and pressure, in order to ensure the melting butt quality, the shorter the switching cycle, the better.

8. Melting Butt: It is the key of welding, the butt process should always be carried out under the melting pressure, the width of the side roll with 2-4mm is appropriate; Pressure should be appropriate, too much pressure will lead to melt all be squeezed away, but not firmly connected.

9. Cooling: Keep the docking pressure unchanged, and let the interface cool down slowly. The cooling time is subject to the stiff crimping by hand and no heat can be felt.

Tee welding


Heat absorption and cooling schedule of PE Pipe:

Wall Thickness mm Pipe Heat Absorption Times Maximum Time Allowed For Switch s Pressurized Cooling Time Cooling Time min
<4.5 45 5 5 6
4.5-7 45-70 5-6 5-6 6-10
7-12 70-120 6-8 6-8 10-16
12-19 120-190 8-10 8-11 16-24
19-26 190-260 10-12 11-14 24-32
26-37 260-370 12-16 14-19 32-45
37-50 370-500 16-20 19-25 45-60
50-70 500-700 20-25 25-35 60-80

The cooling time of welded nozzle is generally 10-12 times the thickness of pipe wall.


GET IN TOUCH
If you would like to have a question then get in touch today, 
we are ready to assist 24/7.
We welcome your cooperation and we will develop with you.
Product Inquiry

Efficient   .   Sustainable   .   Innovative

Waysail specializes in sustainable and environmentally marine and aquaculture solutions, based on many years of experience in the supply and installation of all types of mooring systems, from aquaculture farms to single boat moorings.

Aquaculture Mooring

Fish Cages & Net

Rigging Hardware

Copyright  2007 - 2025 Qingdao Waysail Ocean Technology Co., Ltd
We use cookies to enable all functionalities for best performance during your visit and to improve our services by giving us some insight into how the website is being used. Continued use of our website without having changed your browser settings confirms your acceptance of these cookies. For details please see our privacy policy.
×